If you are using PNPSCADA as an MDUS (Meter Data Unification System) to connect meters to SAP, you can now create Virtual SAP Meter Reading Orders, by going to Tools->Create Virtual MDUS readings'.
These readings will not be sent to SAP. However you can create status 9 SAP readings (on demand) with this transaction, for all the registered registers on a Meter, as registered from SAP.
This is handy for instance when dealing with meters that do not have their own TOU registers, since PNPSCADA would fabricate them. Also for meters that are part of summated accounts, concerning the kVA and TOU registers reported to SAP individually. Also taking into account, that the readings returned would be unscaled.
Please note that the Virtual status of meter readings are now also shown when looking at the MDUS meter reading log, and it can also be filtered on by specifying different selections on the selection screen of the report.
This function is also available as a Web Service at mdusCreateReading.jsp
Normal login details must be specified, and also the relevant MDUS needs to be the selected entity as per the normal parameters of the restful Web Services in PNPSCADA described in http://www.pnpscada.com/webservices.jsp
The additional parameters to pass are:
SNUMBER - meter serial number
start - date and time of the reading, in YYYY-MM-DD HH:MM:SS format
Source - this should be 1 for MDUS or 2 for Meter
The reply would be in a format like the following (as an example):

SUCCESS
12345678

2
1234567890

-1
true
10000234
PEAK
false
1234.235


-2
true
10000235
STANDARD
true


-3
false


The fields above are self evident. If you need more explanation, please ask.

Avatar

sdg.marinusvz
2015-04-29 09:36

The following has been transcribed from an email
Hi Marinus

Please assist with the webservice URL.
The URL I created looks like this : https://arni.pnpscada.com/readMeterTotals?LOGIN=coct.lbonze&PWD=password&SNUMBER=55090920&startdate=2015-04-01&enddate=2015-04-23&Source=1

I doesn?t seems to work.

-27
55090920
102258162
L-SEASON O/PEAK
9
2015-04-23 00:00:00
2015-04-25 08:05:15.874
null
1330.244000
1
1
Y
-1
none
-1
rollback update
-28
55090920
102258162
L-SEASON STD
9
2015-04-23 00:00:00
2015-04-25 08:05:15.878
null
2738.258000
1
1
Y
-1
none
-1
rollback update
-29
55090920
102258162
L-SEASON PEAK
9
2015-04-23 00:00:00
2015-04-25 08:05:15.856
null
1302.672999
1
1
Y
-1
none
-1
rollback update
-30
55090920
102258162
H-SEASON O/PEAK
9
2015-04-23 00:00:00
2015-04-25 08:05:15.842
null
412.558000
1
1
Y
-1
none
-1
rollback update
-31
55090920
102258162
H-SEASON STD
9
2015-04-23 00:00:00
2015-04-25 08:05:15.886
null
770.914999
1
1
Y
-1
none
-1
rollback update
-32
55090920
102258162
H-SEASON PEAK
9
2015-04-23 00:00:00
2015-04-25 08:05:15.869
null
435.639999
1
1
Y
-1
none
-1
rollback update
-33
55090920
102258162
TOTAL POS KWH
9
2015-04-23 00:00:00
2015-04-25 08:05:15.86
null
6990.282999
1
1
Y
-1
none
-1
rollback update
-34
55090920
102258162
PEAK/STD MX DEM
9
2015-04-23 00:00:00
2015-04-25 08:05:15.849
null
1.479772
1
1
Y
-1
none
-1
rollback update
-35
55090920
102258162
MAX DEM KVA
9
2015-04-23 00:00:00
2015-04-25 08:05:15.864
null
1.479772
1
1
Y
-1
none
-1
rollback update
-36
55090920
102258162
OFF PEAK
9
2015-04-23 00:00:00
2015-04-25 08:05:15.846
null
1742.802999
1
1
Y
-1
none
-1
rollback update
-37
55090920
102258162
PEAK AND STD
9
2015-04-23 00:00:00
2015-04-25 08:05:15.852
null
5247.480000
1
1
Y
-1
none
-1
rollback update
-38
55090920
102258162
TOTAL NEG KWH
9
2015-04-23 00:00:00
2015-04-25 08:05:15.883
null
0.000000
1
1
Y
-1
none
-1
rollbac

Avatar

ctmalan
2015-05-13 12:19

The default setting should be from the MDUS with an option to read from the meter.
The serial number should be persistent please, enabling different read dates from the same device.